Design Project of Benicarló's WWTP

Castellon, Spain

  • Markets:

    LANDSCAPE DESIGN , ENVIRONMENTAL STUDIES & PLANNING ,

  • Services:

    ARCHITECTURE & DESIGN ENGINEERING STUDIES ENVIRONMENTAL SERVICES

  • Client:

    Generalitat Valenciana / EPSAR (Entidad Publica de Saneamiento de Aguas Residuales)

The Benicarlo's WWTP (Castellon) is located in a plot defined by the Villaperdiz Landplaning Plan , in the confluence of Pandols river and Cervera river.

  • Include:

    WWTP

  • Cost:

    € 13.108.261,86

  • Status:

    Completed

Due to its nature, the project of Benicarló´s WWTP (Castellón) presents few design technical conditions determined by the presence of elements related to the process of purification, which restricts the measures of landscape integration to installation perimeter elements.

The PRV1b plot treatment (50 m band protection ) between the road CV-135 and the plot PID2, will be realized by the simultaneous objectives of supporting the characteristics of the environment and to obtaining the maximum conceal- ment of the infrastructures. There will be implementing by:
•        The olive trees conservation and protection and existing carob-trees in the band of servitude (PRV1b) and also in the plot PID2.
•    The micro topographic modification.
•    The olive trees and carob-trees transplants from PID2 to PRV1b (16 units). 
 