We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept All”, you consent to the use of ALL the cookies.
A new installation to assume the treatment of residual water was necessary because of the increase of population
Consulting, Project Management
WWTP
€ 45.725,20
Completed 2009
The treatment of the waste water of Benicarló's municipality was realized by a small WWTP located next to Rambla de Cervera.
The increase of the population in the locality during last decade has generated an excess of the treatment capacity . For this reason, the execution of a new installation with sufficient aptitude to assume the treatment of the whole residual water of the municipality was necessary.
The projected WWTP will supply more than 100.000 equivalent inhabitants and the design project develops characteristics gathered in the Developing Plan of the WWTP, with environmental authorisation (DIA).
• Environmental Impact assessment
• Archaeological study
• Landscape study
• Control of risks of serious accidents
• Control and prevention of the legionelosis
• Construction waste management study
• Acoustic study
• Authorization of spillage
• Authorization request for public hydraulic domain occupation
We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept All”, you consent to the use of ALL the cookies.
Environmental Impact Study of the WWTP of Benicarlo
Benicarlo Castellon, Spain
Markets:
URBAN PLANNING , WASTEWATER TREATMENT & REUSE , ENVIRONMENTAL STUDIES & PLANNING ,
Services:
ARCHITECTURE & DESIGN ENGINEERING STUDIES CONSTRUCTION MANAGEMENT ENVIRONMENTAL SERVICES PROGRAM, ADVISORY & PROJECT MANAGEMENT
Client:
Generalitat Valenciana / EPSAR (Entidad Pública de Saneamiento de Aguas Residuales)